Start an Application

What Kind of Permit Do I Need?

 

Some minor activities that are exempt from permitting or fall below permitting thresholds do not require a regulatory permit. Other common projects may qualify for a General Permit (GP). Any activities that do not qualify for an exemption or General Permit and that trip permitting thresholds (see bottom of page) will require an Individual Permit. The differences between these permit types are processing time, submittal requirements and fee amounts.

 

Go through the qualifications in the table below to determine what type of permit you will need for your project. When you have determined what type of permit you need, click the relevant button in the right-hand column. You will be taken to a page that tells you exactly what parts of the Joint Application you need to fill out along with step-by-step instructions to help you fill out a complete application.

 

If your project is in, on, or over the water:

Most lands including - but not limited to - tidal lands, islands, sand bars, shallow banks, and lands waterward of the ordinary high water line or mean high water line, beneath navigable fresh water or beneath tidally influenced waters were titled to the State of Florida when it became a state on March 3, 1845. Title to these lands is held by the Board of Trustees of the Internal Improvement Trust Fund of the State of Florida. The State is responsible for maintaining these submerged lands for a reasonable degree of public use and access, and to protect the lands for future public use.

 

Some of the above described submerged lands have been conveyed (deeded to others) and some waters have been artificially created. See the document "Proprietary and Regulatory Authority" for more information about state-owned submerged lands.

 

If your project is in, on, or over state-owned submerged lands, proprietary authorization may be required even if you do not need a regulatory permit (ERP). There are different construction requirements for projects in different Florida waters (such as OFW's and Aquatic Preserves). If you are building a dock, pier or marina, see the help document "Construction Criteria for Docks, Piers, and Marinas" before applying for a permit.

 

Beginning October 1, 2013 there will be one application for use in the entire state.

 

 

Type of Permit Qualifications Get Started
Exemption Some activities that do not cause a significant amount of individual or cumulative impacts, or that fall below permitting thresholds are exempt from regulatory permitting by DEP.
 
Read the lists of exemptions under Rules 62-330.051 and 62-330.0511, F.A.C., Section 403.813, F.S.,and Section 373.406, F.S. to determine if your project qualifies for an exemption.
 
Most regulatory exemptions claimed for works in, on or over state-owned submerged lands will still require proprietary authorization before the activity is conducted. Exceptions to this requirement are listed in Section 18-21.005(a), F.A.C. Some regulatory exemptions may qualify for proprietary Consent by Rule, meaning that no additional written authorization is required. Projects qualifying for Consent by Rule are listed in Section 18-21.005(b), F.A.C.
 
All exemptions are subject to the conditions described in the applicable rule, and all drawings, plans and activities must comply with all conditions of the exemption.  If your project or activity does not fit all conditions of the exemption, you must apply for a General Permit or Individual Permit.
 

 

 

 

General Permit (GP) This is a type of permit issued by DEP for certain kinds of common minor projects under Chapter 62-330, F.A.C. It requires the applicant to provide notice to DEP at least 30 days before any work can begin.
 
Read the list of General Permits and review the appropriate linked rule section to determine if your project qualifies.
 
All General Permit activities are subject to the conditions described in the applicable rule, and all drawings, plans and activities must comply with all conditions of the Noticed General Permit.  If your project or activity does not fit all conditions, you must apply for an Individual Permit.
 

Individual or
Conceptual Approval
Permit

If your project does not qualify for an exemption or General Permit and it exceeds permitting thresholds, it will require an Individual Permit. Individual permits require individual (project by project) review. There are two types of individual permits:

 

1. Individual Permit

    • Any project or activity that does not qualify to be processed as an Exemption or General Permit.

 

2. Conceptual Approval Permit

    • A Conceptual Approval Permit is a type of individual permit approving the concept of a master plan for a project, which is binding on the DEP and the permittee. This is usually done for large or phased projects where there may be some uncertainty about the final plan. It approves a well-defined project concept and any future changes that remain within the limits of the concept if the provisions in Section 62-330.055 F.A.C (Urban Infill) or Section 62-330.056, F.A.C. (Other Conceptual Approval Permits). are met.

  1. Unless otherwise stated in the permit, issuance of a conceptual approval permit does not authorize construction, alteration, operation, maintenance, removal or abandonment of a project, and does not relieve the holder of such permit of any requirements to obtain a permit for the activities. An application for construction authorization of the first phase of the project also may be included as a part of the initial application. As the permittee desires to construct, alter, operate, maintain, abandon, or remove additional phases, new applications for such activities shall be processed as an application for an individual permit, consistent with the terms and conditions of the issued conceptual approval permit.

    • Additional phases of a Conceptual Approval Permit for Urban Infill and Redevelopment projects can be authorized under a General Permit for that activity.

 

 

 

Joint Coastal Permit
For activities that affect the movement of sand along natural, sandy beaches along the Atlantic or Gulf coasts, e.g., beach restoration, beach nourishment, inlet dredging with sand bypassing, jetties, groins, breakwaters, and revetments that extend into the water. Also includes navigational dredging for deepwater ports.

A Joint Coastal Permit is a combination of an environmental resource permit and a coastal construction permit, and is reviewed and issued by DEP's Bureau of Beaches and Coastal Systems.

 

A Joint Coastal Permit is required for activities that meet all of the following criteria:

  • Located on Florida's natural sandy beaches facing the Atlantic Ocean, the Gulf of Mexico, the Straits of Florida or associated inlets;
  • Activities that extend seaward of the mean high water line;
  • Activities that extend into state-owned submerged lands; and
  • Activities that are likely to affect the distribution of sand along the beach.

 

Activities that require a joint coastal permit include beach restoration or nourishment; construction of erosion control structures such as groins and breakwaters; public fishing piers; maintenance of inlets and inlet-related structures; and dredging of navigation channels that include disposal of dredged material onto the beach or in the nearshore area.

 

For projects that require a Joint Coastal Permit, but also require substantial stormwater treatment systems, you may also be required to apply to your local district office for an ERP stormwater permit.  

 

Contact DEP's Bureau of Beaches and Coastal Systems for more information.
Permitting Thresholds  
Activities that do not exceed certain thresholds do not require a permit from FDEP or the Water Management Districts.
 
The 10/2 Stormwater General Permit requires notification through electronic self-certification, but does not require a permit.
 
 

Unless it is not regulated or is exempt under subsection 62-330.020(1), F.A.C., a permit is required for any activity that, by itself or in combination with any other activity conducted after October 1, 2013, cumulatively exceeds any of the thresholds in paragraphs 62-330.020(2)(a) through (j), F.A.C. Some provisions of those thresholds are explained below:

 

Permitting Thresholds (Subsection 62-330.020(1), and (2)(a) through (j), F.A.C.)

 

(1) A permit under this chapter is not required for activities that qualify for:

(a) Operation and routine custodial maintenance of projects legally in existence, provided the terms and conditions of the permit, exemption, or other authorization for such projects continue to be met, and provided the activity is conducted in a manner that does not cause violations of state water quality standards. However, this exemption shall not apply to any project that is altered, modified, expanded, abandoned, or removed;

(b) An exemption listed in Rule 62-330.051, F.A.C., or in section 1.3 (District-specific exemptions) of the applicable Volume II;

(c) The “grandfathering” provisions of Sections 373.4131(4), 373.414(11), (12)(a), (13), (14), (15), or (16), F.S.; or

(d) The “10/2” general permit for upland stormwater systems authorized in Section 403.814(12), F.S.

(2) Unless the activity qualifies under subsection (1), above, a permit is required prior to the construction, alteration, operation, maintenance, removal, or abandonment of any new project that, by itself or in combination with an activity conducted after October 1, 2013, cumulatively results in any of the following:

(a) Any project in, on, or over wetlands or other surface waters;

(b) A total of more than 4,000 square feet of impervious and semi-impervious surface areas subject to vehicular traffic;

(c) A total of more than 9,000 square feet impervious and semi-impervious surface area;

(d) A total project area of more than one acre;

(e) A capability of impounding more than 40 acre-feet of water;

(f) Any dam having a height of more than 10 feet, as measured from the lowest elevation of the downstream toe to the dam crest;

(g) Any project that is part of a larger common plan of development or sale;

(h) Any dry storage facility storing 10 or more vessels that is functionally associated with a boat launching area;

(i) Any project exceeding the thresholds in section 1.2 (District-specific thresholds) of the applicable Volume II; or

(j) Any modification or alteration of a project previously permitted under Part IV of Chapter 373, F.S.

Construction and operation of the above projects are subject to the additional limitations in paragraph 3.1.4(f) of Volume I.

 

Contact your Local DEP District Office for more information.