Erosion, Sedimentation and Turbidity Controls

The following are excerpts from the Florida Stormwater Erosion and Sedimentation Control Inspector's Manual:

 

On average, Florida receives 40 to 60 inches of rain each year from about 130 storm events. While about 80% of the storms are small, with less than 1 inch of rainfall, the state also experiences torrential downpours and hurricane rains. These cause runoff carrying sediment, fertilizers, pesticides, oil, heavy metals, bacteria, and other contaminants to enter surface waters, causing adverse effects from increased pollution and sedimentation. The implementation of erosion control measures consistent with sound agricultural and construction operations is essential to minimizing these impacts.

 

Florida's stormwater regulatory program requires the use of best management practices (BMPs) during and after construction to minimize erosion and sedimentation and to properly manage runoff for both stormwater quantity and quality. BMPs are control practices that are used for a given set of conditions to achieve satisfactory water quality and quantity enhancement at a minimal cost. Each BMP has specific application, installation, and maintenance requirements that should be followed to control erosion and sedimentation effectively. Accepted engineering methods must be used in the design of these control measures, such as those established by the Florida Department of Environmental Protection (FDEP), Florida Department of Transportation (FDOT), U.S. Department of Agriculture’s (USDA) Natural Resources Conservation Service (NRCS), International Erosion Control Association (IECA), American Society of Civil Engineers (ASCE), U.S. Army Corps of Engineers (USACOE), or other recognized organizations.

 

7 Principles of Erosion and Sediment Control (From Chapter 1.6)

 

For an erosion and sedimentation control program to be effective, it is imperative that provisions for control measures be made in the planning stage. These planned measures, when conscientiously and expeditiously applied during construction, will result in orderly development without environmental degradation and with cost savings. The seven principles listed below should be used to the maximum extent possible. Usually, these principles are integrated into a system of vegetative and structural measures, along with management techniques, that are used in developing a plan to prevent erosion and control sediment. In most cases, a combination of limited grading, limited time of exposure, and the judicious selection of erosion control practices and sediment-trapping facilities are the most practical methods of controlling erosion and the associated production and transport of sediment.

 

1. Plan the development to fit the particular topography, soils, drainage patterns, and natural vegetation of the site.

Detailed planning should be employed to ensure that roadways, buildings, and other permanent features of the development conform to the natural characteristics of the site. Large graded areas should be located on the most level portion of the site.

 

Slope length and gradient are key elements in determining the volume and velocity of runoff and its associated erosion. As both slope length and steepness increase, the rate of runoff increases and the potential for erosion is magnified. Where possible, steep vegetated slopes should be left undisturbed. Areas with slope and soils limitations should not be used unless sound conservation practices are employed. For instance, where it is necessary to build on long, steep slopes, the practices of benching, terracing, or constructing diversions should be used. Areas subject to flooding should be avoided or used as part of the stormwater management system. Floodplains should be kept free from filling and construction activities since they temporarily store excess runoff, thus helping to avoid erosion and flooding problems downstream.

 

Erosion control, development, and maintenance costs can be minimized by selecting a site suitable for a specific proposed activity, rather than by attempting to modify a site to conform to that activity. This kind of planning can be more easily accomplished where there is a general land use plan based on a comprehensive inventory of soils, water, and other related resources.

 

2. Minimize the extent of the area exposed at one time and the duration of exposure.

When land disturbances are required and the natural vegetation is removed, keep the area and the duration of exposure to a minimum. Plan the stages of development so that only the areas that are actively being developed are exposed. All other areas should have a good cover of either temporary or permanent vegetation, or mulch. Grading should be completed as soon as possible after it has begun. Immediately after grading is completed, a permanent vegetative cover should be established. As cut slopes are made and as fill slopes are brought up to grade, these areas also should be revegetated. This is known as staged revegetation. Minimizing the grading of large or critical areas during the rainy season (the time of maximum erosion potential) reduces the risk of erosion.

 

3. Apply perimeter control measures to protect the disturbed area from offsite runoff and to prevent sedimentation damage to areas below the development site.

These measures effectively isolate the development site from surrounding properties and, in particular, control sediment once it is produced, thus preventing its transport from the site. Diversions, berms, sediment traps, vegetative filters, and sediment basins are examples of practices to control sediment. Vegetative and structural sediment control measures are either temporary or permanent, depending on whether they will remain in use after development is complete. Generally, sediment is retained by (a) filtering runoff as it flows through an area and (b) impounding the sediment-laden runoff for a period so that the soil particles settle out. The best way to control sediment, however, is to prevent erosion, as discussed in the fourth principle.

 

4. Apply erosion control measures to prevent excessive onsite damage.

The use of erosion control measures on a site prevents excessive sediment from being produced. Keep soil covered as much as possible with temporary or permanent vegetation, or with various mulch materials. Special grading methods, such as roughening a slope on the contour or tracking with a cleated bulldozer, may be used. Other practices include diversion structures to direct surface runoff from exposed soil and grade stabilization structures to control surface water. These water control devices must prevent "gross" erosion in the form of gullies. Lesser types of erosion, such as sheet and rill erosion, should be prevented, but often scheduling or the large number of measures required makes this impractical. However, when erosion is not adequately controlled, sediment control is more difficult and expensive.

 

5. Keep runoff velocities low and retain runoff on the site.

The removal of existing vegetative cover and the resulting increase in impermeable surface area during development increase both the volume and velocity of runoff. These increases must be taken into account when providing for erosion control. Keeping slope lengths short and gradients low, and preserving natural vegetative cover, can keep stormwater velocities low and limit erosion hazards.

 

Runoff from the development site should be safely conveyed to a stable outlet using storm drains, diversions, stable waterways, or similar measures. Consideration should be given to installing stormwater detention structures to prevent flooding and damage to downstream facilities resulting from increased runoff from the site. Conveyance systems should be designed to withstand the velocities of projected peak discharges. These facilities should be operational as soon as possible after the start of construction.

 

6. Stabilize disturbed areas immediately after the final grade is attained.

Permanent structures, temporary or permanent vegetation, and mulch, or a combination of these measures, should be employed as quickly as possible after the land is disturbed. Temporary vegetation and mulches can be most effective under conditions where it is not practical to establish permanent vegetation. Such temporary measures should be employed immediately after rough grading is completed if a delay is anticipated in obtaining finished grade. The finished slope of a cut or fill should be stable, and the design should consider ease of maintenance. Stabilize roadways, parking areas, and paved areas with gravel sub-base whenever possible.

 

7. Implement a thorough maintenance and follow-up program.

This last principle is vital to the success of the six other principles. A site cannot be effectively controlled without thorough, periodic inspections of the erosion and sediment control practices. These practices must be maintained, just as construction equipment must be maintained and materials checked and inventoried. An example of applying this principle is to start a routine "end of day check" to make sure that all control practices are working properly.

 

A few examples of commonly used BMP's

 

These are just a few common types of Best Management Practices (BMP's) used to control erosion, sedimentation and turbidity. Chapter 4 of the Florida Stormwater Erosion and Sedimentation Control Inspector's Manual, and the Erosion and Sediment Control Designer and Reviewer Manual contain more BMP's which may be more appropriate for your project. The manual also contains construction drawings and construction plans that can help you properly use the BMP's.

 

Double-row silt fence (Page 45 in the inspector's manual)

 

Silt fence is a perimeter control commonly used along the boundary of the construction area to prevent sediments from moving off-site or into adjacent sensitive environments such as wetlands.

 

Weighted floating turbidity barrier (Page 66 in the inspector's manual)

 

Floating turbidity barriers are used to contain turbid (muddy) water caused by construction of a project in, on or over open water. They are commonly used to surround dock, pier, marina, shoreline stabilization and boat ramp construction sites.

 

Storm drain inlet protection (Page 75 in the inspector's manual)

 

Storm drain inlet protection is used when land will be disturbed near a storm drain to prevent sediments from filling and blocking the storm drain, which could cause flooding.